CASE STUDY

REMEDIAL

Ace Hotel

Contract Value: $1.3 million
Project Duration: 7 months
Project Completed: February 2022

Problem: Bringing the existing heritage façade (structural brickwork and structural lintels) to current BCA and Australian Standards.

Solution: Engaged structural; engineer and undertook insitu integrity testing to develop a remediation and repair methodology for the building elements to ensure compliance with current codes and standards.

Outcome: Avoided replacement of brick façade and lintels by repairing the existing elements. By implementing this forensic and detailed approach to each building element we avoided further demolition and replacement works and improved the programme by 3 months.

THE BREWERY CHIPPENDALE

REMEDIAL

Project Info

Project Description: EP were engaged to undertake heritage facade repair work around window openings. This included substrate repair and preparation for new windows and glazed facades. Additional works included heritage sandstone lintel structural repair works
Contract Value: $850k
Project Duration: 7 months | Completed: July 2023

URBANEST STUDENT ACCOM, ULTIMO

FIT-OUT

Project Info

Project Description: Completed Ground Floor Lobby and Front of House Fitout for Student Accommodation in Ultimo
Contract Value: $750k
Project Duration: 4 months | Completed: 2019

THE GRACE HOTEL, YORK ST

REMEDIAL & FIT-OUT

Project Info

Project Description: EP were engaged to complete repair and extension works for commercial grade kitchen. Additional works included fit-out of new office spaces, and making compliant existing commercial areas to current codes & standards.
Contract Value: $150k
Project Duration: 3 months | Completed: February 2023

CREDIT SUISSE, CIRCULAR QUAY

MAKE-GOOD | FIT-OUT

Project Info

Project Description: Office make-good and fit-out for Credit Suisse Gateway Circular Quay.
Contract Value: $330k
Project Duration: 3 months | Completed: 2021

GARDEN HOUSE, WATERLOO

REMEDIAL

Project Info

Project Description: EP Build were engaged to undertake on behalf of Developer to complete defective and remedial works to a recently completed residential project in Waterloo.
Contract Value: $150k
Project Duration: 3 months | Completed: 2020

CASE STUDY

REMEDIAL

Help Street

Contract Value: $450k
Project Duration: 3 months
Project Completed: May 2022

Problem: The commercial building had fallen into disrepair in areas of the roof, which had caused distress and leaking into the commercial tenancies below.

Solution: EP Build attended site and undertook a detailed inspection and prepared 2 remedial strategies for the client to select from. The preferred option involved chemical injections into the existing structure.

Outcome: Provided 2 alternate building solutions for the strata corporation. The selected option avoided replacement of brick façade and lintels by repairing the existing elements. By focusing on the specific building leaks and tracking them, we were able target the specific areas of the building that were encouraging water penetration and treated the source of the issues.

SILKARI, CHATSWOOD

FIT-OUT

Project Info

Project Description: Completed Ground Floor Lobby and Front of House Fitout for recently completed serviced apartments/hotel in Chastwood
Contract Value: $210k
Project Duration: 4 weeks | Completed: 2022

SUTHERLAND ST, CREMORNE

REMEDIAL

Project Info

Project Description: Engaged to undertake remedial works to existing apartment building. This included balcony repairs, repairing severe concrete cancer and brick façade repairs.
Contract Value: $420k
Project Duration: 5 months | Completed: 2020

ALFRED ST, MILSONS POINT

REMEDIAL & FIT-OUT

Project Info

Project Description: Engaged to undertake remedial works to existing apartment building. This included balcony repairs, re-waterproofing and tiling balconies, and undertaking balustrade repairs.
Contract Value: $360k
Project Duration: 4 months | Completed: 2021

NAVITAS, ELIZABETH ST, SYDNEY

MAKE-GOOD | FIT-OUT

Project Info

Project Description: EP were engaged to complete repair works for collapsed feature ceiling and also complete a fitout for new class rooms in an educational facility in
the Sydney CBD.
Contract Value: $100k
Project Duration: 4 weeks | Completed: February 2023

VICTORIA RD, EPPING

REMEDIAL

Project Info

Project Description: Engaged to undertake remedial works to existing apartment building. This included balcony repairs, repairing severe concrete cancer and brick façade repairs.
Contract Value: $280k
Project Duration: 2 months | Completed: 2021

MARINE, MAROUBRA

REMEDIAL

Project Info

Project Description: Removal and replacement of combustible cladding to residential apartment in Maroubra  |  Repainting façade  |  Repair corrosion and protect building elements from marine environment

Contract Value: $800k million
Project Duration: In Progress

HAMPDEN ST, CREMORNE

REMEDIAL

Project Info

Project Description: Project Description: Removal and replacement of combustible cladding to residential apartment in Cremorne

Contract Value: $450k
Project Duration: In Progress

BRUCE ST, BRIGHTON

PROJECT MANAGEMENT & CONSTRUCTION SIDE REMEDIAL

Project Info

Project Description: Removal of combustible cladding and replacement with compliant cladding to residential apartment in Brighton

Contract Value: $700k
Project Duration: 12 weeks

RYDE GARDEN

REMEDIAL

Project Info

Project Description: Intrusive investigations of bathrooms and balconies on behalf of the owners corporation. Works included complete demolition, instructive investigations and reconstruction of bathrooms and balconies

Contract Value: $350k
Project Duration: 6 weeks